Project report
PROJECT REPORT

Relocation of production at automotive supplier led out of the crisis

  • Improvements realized through lean management and lean production
  • Technical improvements and new production planning eliminate bottlenecks
  • 12 of 15 production lines relocated to the new site on schedule
Interim Executive for production optimization and relocation

Interim Executive for production optimization and relocation

  • Management, plant and production management (mechanical engineering, automotive)
  • Project manager for factory planning and production relocation
  • Lean management and lean production in large and small series

In a crisis situation, the interim manager took over the position of managing director at the Polish plant of a German group of companies on a temporary basis in 2018. The group is one of the top 50 in the German automotive supply industry and is a tier 1 supplier of drive shafts and joints. Its main customers are premium OEMs in Europe, Asia and North America. The manufacturers primarily install these components in their four-wheel drive or rear-wheel drive models.

The young Polish plant was to expand the company's range by taking on new products. The plan was to relocate the products, including production facilities, from an OEM in Germany, release them in Poland and then ensure customer supply to Germany. This project ran very smoothly. The situation threatened to escalate: High delivery backlogs, daily bottleneck coordination with the customer at management level, quality problems in production and considerable dissatisfaction among the site's management team were unmistakable signs of the crisis. The relocation project was in an extremely critical phase.

In the end, the management was restructured. As a temporary managing director, the interim manager was tasked with the following tasks:

  • Stabilize customer supply
  • Improve efficiency in production
  • Gain back customer trust
  • Lead through clear and authentic communication
  • Continue the production relocation with realistic project management
  • Develop the site including organization and processes

Implemented improvements through lean management and lean production

The interim manager started immediately, together with managers, employees, customers and suppliers to identify weak points. This revealed shortcomings in plant availability/OEE, quality inspection and on-site crisis management in particular. Within days, the interim manager developed an emergency plan with the teams. On this basis, a comprehensive action plan was created within 4 weeks, which included all areas of the plant.

The interim manager intensified the visualization of production using key figures and introduced a daily store floor round in production. Information was shared there and decisions were now made quickly. The visualization helped employees to monitor and increase output on a shift-by-shift basis.

The interim manager took a look at every production line and plant area during daily gemba walks with the managers. He had the managers define action and improvement measures, which were then jointly reviewed in terms of implementation and effectiveness. The interim manager used proven lean management and lean production tools, such as value stream mapping, to plan and monitor success.

Technical improvements and new production planning eliminate bottlenecks

In order to eliminate bottlenecks in the production lines, the interim manager appointed machine suppliers, specialists from the German plant and experts for difficult machining processes to the plant. Their expertise made a significant contribution to increasing throughput, reducing reject rates and achieving a much more stable quality performance through numerous technical improvements.

He also improved efficiency by ensuring that maintenance activities were no longer carried out ad hoc, but were scheduled, prepared and the operating personnel were actively involved. Additional internal training directly on site and courses at specialist companies also helped to build up a technically skilled team. Production planning now takes all maintenance work into account and reduces the number of set-up operations. Production time was temporarily extended into the weekend.

12 of 15 production lines relocated to the new site on time

Within 4 weeks, customer supply was ensured. After 4 months, the delivery backlog had been almost completely eliminated and the relationship with the customer had eased considerably. The reject rate was continuously reduced over the course of the year and production output stabilized at a high level.

After stabilization, the interim manager set the next phase of the relocation project on a new realistic timeline. During the mandate, a total of 12 of the final 15 production lines and around 80 of the final 100 part numbers were relocated in line with the program.

Management structure at the site set up for the future

The interim manager worked together with HR consultants to set up the new management team with Polish managers and employees (for logistics, production, project management, controlling, plant and management). He was able to fill the vacant positions with excellent candidates in close consultation with the German management. This also included the new Polish managing director, to whom the interim manager handed over his responsibilities after 17 months.

Beforehand, the interim manager had defined the corporate strategy for the site together with the German management. In this context, he implemented the necessary restructuring measures and business planning for the following years, which was secured by acquiring two new customer orders thanks to the plant performance achieved.

read more read less
Interim Executive for production optimization and relocation

Interim Executive for production optimization and relocation

  • Management, plant and production management (mechanical engineering, automotive)
  • Project manager for factory planning and production relocation
  • Lean management and lean production in large and small series
Created by Charly Kahle on 11.02.2025
Last updated on 16.04.2026

Projects
by this manager

Symbolic image for the construction of a new automotive production facility in Eastern Europe

Establishment of a new automotive production facility in Eastern Europe

An OEM had commissioned a medium-sized German automotive supplier to set up a new production facility in an Eastern European EU country. The OEM wanted to start vehicle production there. The company engaged the interim manager with proven experience in plant construction and production relocations in Eastern Europe.

Restructuring of a large production plant

Restructuring of a large production plant

The largest production company (700 employees) of a medium-sized ...

You might also be
interested in this

The picture shows a young woman looking at her smartphone.

FAQ: What is Interim Management?

Answers to all your questions about interim management
Special topic: Ways out of the crisis. The picture shows a thoughtful crisis manager.

Ways out of the crisis

Brochure: Proven Best Practices for Reorganization, Restructuring, and Turnaround
The picture shows an interim manager specializing in pharmaceuticals and medical technology.

Pharmaceuticals and Medical Technology

Brochure: Custom Solutions for Today's Challenges
The image shows a graphic symbolization of the Connected Workforce.

Connected Workforce

Brochure: Building a Connected Workforce Through Interim Management
The picture shows an interim manager on a puzzle piece.

10 Essential Features

Pocket Guide: How Companies Can Identify Suitable Interim Professionals
The picture shows the figure of an interim manager surrounded by hanging carrots.

Recruitment Methods

Pocket Guide: How Companies Can Find the Right Specialists and Executives