Project report
PROJECT REPORT

Restructuring of a large production plant

  • Analysis reveals a number of problems in production and management
  • Cost improvement plan drawn up for the economic processing of orders
  • Cost drivers in production identified and costs reduced by up to 20 percent
Interim Executive for production optimization and relocation

Interim Executive for production optimization and relocation

  • Management, plant and production management (mechanical engineering, automotive)
  • Project manager for factory planning and production relocation
  • Lean management and lean production in large and small series

The largest production company (700 employees) of a medium-sized family business had fallen into a veritable crisis. With a turnover of 193 million euros, the losses amounted to a double-digit million figure. As a result, the management of the holding company hired the interim manager with restructuring experience as managing director of the subsidiary in order to draw up a realistic and sustainable restructuring plan. One of the requirements was that the restructuring should not damage the company's very good image as a family business and regionally important employer with a recognized high level of social responsibility.

Analysis reveals a number of problems in production and management

At the time the mandate was taken on, the company had already been without management or plant management for almost two years. As the interim manager discovered in the analysis, this was one of the reasons why a number of problem areas had emerged. These included:

  • The company had no suitable mechanisms in place to process the volatile orders economically. Excessive and uneconomical use of temporary staff was one of the consequences.
  • The structural staff department was bloated, inefficiently organized and employees were unaware of their individual contribution to the company's success. The management team was also not focused on a single goal and "silo thinking" had taken over.
  • In addition, the launch of a new product generation that was important for the future success of the business was highly jeopardized. Due to the inexperience of the project members, project management, timelines, costs and investment planning urgently needed to be improved.

Cost improvement plan developed to process orders economically

As a first step on the way to improving performance, the interim manager developed a cost improvement plan, which began with a hiring freeze. Exceptions were only made for urgently needed specialists and managers. He compensated for the fluctuation of individual employees by reassessing and redistributing tasks. He countered the volatile workload by working with production management and supply chain management to strictly adjust the number of temporary workers to actual demand and also increased the capacity of individual production areas by changing shift models. Furthermore, he pushed for the expansion of employee qualifications in order to achieve their ability to work at several workstations and thus ensure better capacity balancing in the event of fluctuating workloads.

For further optimization, the interim manager reviewed all planned expenditure. He reassessed the planned investments and only realized those with proven necessity and/or appropriate ROI.

Cost drivers in production identified and costs reduced by up to 20 percent

In the analysis, the interim manager identified the production processes "set-up and TPM" and "welding processes" as cost drivers. In order to reduce costs, he optimized these processes in collaboration with those responsible. In this way, plant availability was increased and process reproducibility improved. This not only reduced error costs, but also shortened throughput times. As a result, the production costs of certain products were reduced by up to 20 percent.

Managers focused on measures and targets and "silo mentality" reduced

In order to win over managers and employees for the implementation of the cost improvement plan, the interim manager pursued a transparent communication strategy from the outset. He explained the situation and the measures required to reduce costs and improve results to the plant team.

In addition, he assigned clearly quantified tasks and targets to each manager in the plant team, which were reviewed on a monthly basis. He reassigned individual management tasks. In this way, the interim manager succeeded in aligning the managers to common measures and goals and reducing "silo thinking".

Reorganizing project management for the start-up of a new product generation

In order to ensure the production of the product generation that was important for the success of the business, the interim manager realigned the project management for the start-up. In particular, he recalculated the costs and updated the profitability calculation. The creation of a new schedule and consistent change management contributed significantly to the successful launch of the innovation.

In addition, he used the production processes that had changed with the new product to consolidate the layout of some production areas, thus freeing up space.

Concept developed for fundamental restructuring with staff reductions

After the interim manager had laid the foundation for the restructuring with the cost improvement plan, he developed a concept for the sustainable structural improvement of the company. To this end, he determined the break-even point and the target costs based on a specified multi-year sales and volume plan. As a result, he proposed to the management and supervisory board that around 30 percent of jobs be cut over the next two years, particularly in the area of structural personnel. The company owners agreed to this proposal.

Balancing of interests and redundancy plan negotiated with the works council

Following the decision, the interim manager was able to negotiate a legally compliant balancing of interests and redundancy plan tailored to the needs of the plant within three months with the help of specialist lawyers. The implementation of the personnel measures contained in the plan and the associated organizational and structural changes began immediately after it was adopted.

Restructuring proves successful and| savings targets exceeded

The interim manager's consolidation course was already successful in the 2023 financial year. The savings targeted in the budget planning at the end of 2022 were exceeded by more than 50%. The planning for 2025/26 forecasts a balanced plant result - with losses at roughly the same level as in 2022.

New product generation launched on time and on budget

The new product generation was raised to an unprecedented level of quality through consistent progress tracking and continuous process improvement in production, and the SOP was completed on time and within the specified budget.

The condensed and optimized layout of the plant also enables the addition of further products and services.

read more read less
Interim Executive for production optimization and relocation

Interim Executive for production optimization and relocation

  • Management, plant and production management (mechanical engineering, automotive)
  • Project manager for factory planning and production relocation
  • Lean management and lean production in large and small series
Created by Charly Kahle on 11.02.2025
Last updated on 16.04.2026

Projects
by this manager

Symbolic image for the construction of a new automotive production facility in Eastern Europe

Establishment of a new automotive production facility in Eastern Europe

An OEM had commissioned a medium-sized German automotive supplier to set up a new production facility in an Eastern European EU country. The OEM wanted to start vehicle production there. The company engaged the interim manager with proven experience in plant construction and production relocations in Eastern Europe.

463_1403_relocation_production_automotive_driveshaft_joints_project_management

Relocation of production at automotive supplier led out of the crisis

In a crisis situation, the interim manager took over the position of managing director at the Polish plant of a German group of companies on a temporary basis in 2018. The group belongs ...

You might also be
interested in this

The picture shows a young woman looking at her smartphone.

FAQ: What is Interim Management?

Answers to all your questions about interim management
Special topic: Ways out of the crisis. The picture shows a thoughtful crisis manager.

Ways out of the crisis

Brochure: Proven Best Practices for Reorganization, Restructuring, and Turnaround
The picture shows an interim manager specializing in pharmaceuticals and medical technology.

Pharmaceuticals and Medical Technology

Brochure: Custom Solutions for Today's Challenges
The image shows a graphic symbolization of the Connected Workforce.

Connected Workforce

Brochure: Building a Connected Workforce Through Interim Management
The picture shows an interim manager on a puzzle piece.

10 Essential Features

Pocket Guide: How Companies Can Identify Suitable Interim Professionals
The picture shows the figure of an interim manager surrounded by hanging carrots.

Recruitment Methods

Pocket Guide: How Companies Can Find the Right Specialists and Executives